PROTECT YOURSELF with Orgo-Life® QUANTUM TECHNOLOGY
Orgo-Life the new way to the future Advertising by AdpathwayChile · Mining
Key Facts
—Cause. A severe winter storm in the Atacama Region damaged two transmission towers, cutting grid power to the Caserones mine on 18 July 2026.
—Duration. Lundin Mining expects a total power restoration and gradual restart within two to three weeks from its 27 July update.
—Production. Analysts estimate the outage exposes roughly 8,400 to 10,900 tonnes of scheduled copper output based on daily run rates.
—Guidance. Lundin has maintained its full-year 2026 production guidance of 130,000 to 140,000 tonnes of copper for Caserones.
—Recovery. The company states weather-related disruptions are embedded in annual plans and expects to recover most lost output later in the year.
*A brutal Andean winter storm has tested Chile’s copper supply chain, knocking a major mine offline. Investors are watching whether lost output can be clawed back in a market hungry for metal.*

One-stop reference
Company Intelligence
Every listed company in Latin America — financials, ownership and structure for 1,450+ companies across 26 exchanges, in one place.
How a winter storm paralyzed a copper mine
Heavy rain and unusually heavy snowfall from a severe winter storm battered Chile’s high-altitude Atacama Region in mid-July. Inspections revealed damage to two transmission towers that supply the Caserones mine, completely severing its grid connection on 18 July.
Backup generators are running only critical infrastructure while access roads remain blocked or impaired by snow. Site crews are being rotated safely as repair teams work to restore power and reopen logistics routes.
The production gap and the plan to close it
With Caserones producing an average of about 364 tonnes of copper per day in 2025, a 23-to-30-day outage exposes between 8,400 and 10,900 tonnes of scheduled output. That represents roughly seven to eight percent of the mine’s 2026 guidance midpoint.
Lundin describes this as exposure rather than a permanent loss. The company signals it can offset the shortfall by running the plant harder in the fourth quarter, deferring non-critical maintenance, and optimizing ore grades once grid power is fully restored.
Guidance holds steady despite market nerves
Lundin’s formal 2026 production target for Caserones remains unchanged at 130,000 to 140,000 tonnes of copper and 2,000 to 3,000 tonnes of molybdenum. The company explicitly notes that weather-related disruptions are factored into its annual operating plans.
Analysts caution that the guidance could come under pressure if the fourth-quarter recovery underperforms. For now, Lundin is betting that a gradual restart and a strong finish to the year will keep the mine within its original range.
What it means in a tight copper market
The temporary loss of roughly 10,000 tonnes of Chilean supply arrives in a global copper market already grappling with low inventories and growing demand from the energy transition. Even short-lived disruptions can tighten spot availability and support prices.
Chile is the world’s largest copper producer, and any prolonged outage at a mid-tier mine like Caserones ripples through supply chains. For international investors and diplomats, the episode underscores the physical vulnerability of critical mineral assets to extreme weather in the high Andes.
Restart hinges on power, not plant damage
Lundin has not reported any structural damage to Caserones’ processing plant, crushers, or conveyor systems. The bottleneck is strictly power transmission and site access, not the integrity of ore-handling equipment.
The restart is described as gradual, meaning a staged ramp-up of crushing, conveying, milling, and concentrator circuits once electricity is stable. If repairs stay within the two-to-three-week window, the company expects to bring operations back to normal throughput without major equipment overhauls.
Frequently Asked Questions
What caused the Caserones mine outage?
A severe winter storm in Chile’s Atacama Region damaged two transmission towers, cutting grid power to the mine on 18 July 2026. Heavy snow also blocked access roads.
How much copper production is affected?
Analysts estimate the outage exposes roughly 8,400 to 10,900 tonnes of scheduled copper output, based on the mine’s 2025 daily production average and a 23-to-30-day interruption.
Did Lundin Mining change its 2026 guidance?
No. Lundin maintained its full-year 2026 production guidance of 130,000 to 140,000 tonnes of copper for Caserones, stating weather disruptions are embedded in its annual plans.
When will the Caserones mine restart?
Lundin’s 27 July update guides to a full power restoration and gradual restart within approximately two to three weeks from that date, assuming repairs proceed on schedule.
The Rio Times · Power Map
See who really holds power in Latin America
Click to open the Power Map →


2 hours ago
2



















English (US) ·
French (CA) ·
French (FR) ·